C of O obtained. Daniel and Bobby have a few more items to complete.

Electrical Update

Magnolia has had the electrical pole set, and our electrician has been there and will be done tomorrow. We are waiting on our HVAC company to get the gas lines in to have that placed.

House Set 12/29/2022

The house set went very well today. I didn’t get my full walkthrough, but I will complete that tomorrow. Overall, the house looks fantastic. There are a few cracks, paint is slightly irregular, but the house set was done very well. The property is very muddy; if...

Update for Magnolia

Per the concrete shortages, we have to postpone the Magnolia build. Kenny and Stuart Meade our going to stake out on 11/18/2022. The new tentative set date is 12/15/2022.