The Journey Through the Building Process
Overall Job Completion
- Overall Completion 100%
SET DATE: 12/15/2022
Pre-construction Phase
- First Visit 100%
- Site Visit 100%
- Sales 100%
- Workbooks Created 100%
- Health Permit (Septic and Well Permits) 100%
- Building Permit 100%
- Construction Preview 100%
Utilities
- Electric Application 100%
- Electrical Engineering Meeting 100%
- Natural Gas or Propane Application 100%
- Natural Gas Engineering Meeting 100%
Construction Phase
- Workbooks Review 100%
- Escavation (Hole Dug) 100%
- Footers Poured 100%
- Foundation Poured (Walls) 100%
- Foundation Floor Poured (Garages and Basements Only) 100%
- Sill Plates Installed 100%
- Partial Back Fill 100%
- Egress Windows and Jackposts Ordered 100%
- House Set 100%
- Garage Build 100%
- Electrical Installed 100%
- Gas Installed 100%
- HVAC Installed 100%
- Plumbing Finished 100%
- Gutters Installed 100%
- Flatwork (Sidewalks, Porch Caps, and/or Driveway) 100%
Fit & Finish
- Marriage Line 100%
- Drywall Repairs 100%
- Fit & Finish 100%
Aftermarket
- 6 Months 100%
- 1 Year 100%
Certificate of Occupancy
- Electrical Inspection 100%
- Mechanical Inspection 100%
- Plumbing Inspection 100%
- Final Inspection 100%
Notes
Certificate of Occupancy Obtained
C of O obtained. Daniel has a small list (siding) to complete.
Update
Hubbard has finally been inspected for mechanicals. Once the gas meter is in all that we are waiting on the stoops to be finished, this house will be done, and we will call in for inspections for CoO.
Electrical Update
I stopped by today and saw that the electricity had been turned on, and the roof is being turned on as I write this. The flat work will be working on the garage tomorrow. Waiting on the Heating and Cooling company to be able to get the gas on. The garage should be completed tomorrow, and moving on to Magnolia.
Set Day 12-15-2022
Set day was COLD! The house was set without any hitches and was an excellent set. We even had a special visitor, an Elkhart Police Officer. He watched the house get set with us and was very interested in how long it took us so we would stop blocking the road. He asked many questions and seemed like he might know a few people to refer to LaCasa for potentially buying the home.
The house looked good on the inside; the paint needs to be more evenly applied, but few cracks and was evenly built.
Hubbard Updates
Unfortunately, we have had to push the set back the Hubbard set due to concrete shortages and weather.
The new set day is 12/29/2022.
Kenny will stake out with Stuart Meade the house today, 11/18/2022, so that the Hubbard can be excavated as early as tomorrow or Monday, November 21, 2022.